What Is WIP Reporting and Why Is It Important for Contractors?

Writer: Paramita Bhattacharya
Paramita Bhattacharya
6 days ago
2 min read

A WIP (work-in-progress) report is a schedule that shows how every open construction contract is performing financially. It compares what a job has earned with what has been billed. Sureties, banks, and CPAs use it to judge whether a contractor's jobs, and its financial statements, can be trusted.


Commercial building under construction, a typical project tracked on a contractor WIP schedule

What a WIP Schedule Includes

  • Contract value: original contract plus approved change orders

  • Estimated total cost: current estimate of the total cost to finish the job

  • Estimated gross profit: contract value minus estimated total cost

  • Cost to date: actual costs posted to the job so far

  • Percent complete: cost to date divided by estimated total cost

  • Earned revenue: contract value times percent complete

  • Billed to date: what you have invoiced the customer

  • Overbilling or underbilling: billed to date minus earned revenue

  • Cost to complete: estimated total cost minus cost to date

Overbillings and Underbillings, in Plain Terms

  • Overbilling: you billed more than you earned. It is a liability. It can mean you are managing cash well, or that you are front-loading bills.

  • Underbilling: you earned more than you billed. It is an asset, but sureties look at it closely. Large underbillings can signal billing delays or cost overruns.

Why WIP Reporting Matters for Contractors

  1. It catches losing jobs early. Profit fade shows up month by month, not after the job closes.

  2. It drives your financial statements. Revenue on percentage-of-completion comes from the WIP.

  3. Sureties rely on it. Underwriters compare WIP schedules over time to see if your estimates hold up.

  4. It protects cash. Underbillings point to money you have earned but not collected.

Common WIP Mistakes

  • The WIP does not tie to the general ledger

  • Estimated costs are never updated

  • Change orders are missing or not approved

  • The WIP is only prepared once a year

Want to see how WIP fits into the bigger picture? Read How Financial Statements Impact Your Bonding Capacity.

How SuretyCFO Helps

SuretyCFO prepares a monthly WIP schedule for commercial contractors with $5M to $50M in revenue, tied to the books and reviewed at the CFO level. We are based in Old Bethpage, New York, and work virtually with contractors nationwide.

Comments


SuretyCFO™ provides fractional CFO leadership for bonded trade contractors, subcontractors, and general contractors, focused on accurate financial reporting, working capital stability, and sustainable growth. Serving contractors nationwide, 100% virtual. Call (516) 605-4617.

  • LinkedIn

© 2026 SuretyCFO™. Fractional CFO Services for Bonded Contractors. All rights reserved.

bottom of page